Case Studies
Real fast-track applications that failed. Each case study examines what went wrong, why the panel rejected or halted the application, and how a systematic check would have caught the issue.
Delmore
Rejected (draft decision to refuse)Infrastructure assumptions contradicted Watercare and Auckland Transport plans. The panel found the gaps could not be resolved.
Read the full case studyTrans-Tasman Resources (TTR)
Withdrawn (facing draft refusal)Outdated data, internal contradictions, and a retracted economic claim undermined the entire application.
Read the full case studyStella Passage
Halted by judicial reviewA mismatch between the application scope and the Schedule 2 legislative description cost months of delay.
Read the full case studyTe Kuha
Failed completeness assessmentSeven basic application requirements were not met. The application was returned before it reached the Minister.
Read the full case study